Church-Water Two-Way Conversion

Church-Water Master Map

Project Information

  • Phased design and construction plan: Phasing this project is an important aspect of City support to the businesses located in the affected area to have minimal disruption to businesses and their customers
  • Start Date: June 12, 2017
  • Cost: $11.5 million
  • Contractor: Morrow Construction
  • Next Open House: October 18, 5:30 p.m.
    Museum Atrium
    411 N. Main Street
    Las Cruces, NM 88001
  • Estimated Completion Date: December 31, 2018

Follow the project on Facebook with the City of Las Cruces and Downtown Las Cruces Partnership or on Twitter.

Business Friendly

  • New communication processes to keep you informed. Join our stakeholder email list by emailing us you contact info.
  • April 17, 2017 - City Council approved Resolution Number 17-174 authorizing the contractor to work outside the hours of 7 a.m. to 6 p.m.